Library Expansion and Renovation Project

Image
A rendering of the expanded library space

About the Project

In 2018, the Sun Prairie Public Library staff and the Library Board began an exciting journey to expand and renovate the existing Library. Data and community discussions demonstrated that the Sun Prairie Public Library was undersized for our service population. Additionally, surveys, focus groups, and analysis revealed gaps in modern spaces and features in order to successfully meet service goals. 

The expansion and renovation project will include many forward-thinking features including: a geothermal HVAC, a microgrid system with solar panels and battery energy storage, a makerspace, a library of things collection, a dedicated teen space, a larger youth services programming room, an outdoor amphitheater programming space, a local history and interest collection, more study rooms, a larger Friends bookstore and café space, exposure to local art, and an atrium space which will bridge the expansion and existing library. The renovation will add an additional 25,075 square feet to the space, making the renovated building 60,600.  

In May 2024, the Library Board approved awarding a construction contract to Kraemer Brothers, and a budget amendment was approved by City Council, allowing the construction project to begin. Currently, there is an anticipated completion date of March 2026. 

Walk-through of Conceptual Design

Image

 

Support Our Project 

Helping us on this journey is the Sun Prairie Public Library Foundation and the generous individuals and organizations throughout the Sun Prairie Community that have contributed to the Capital Campaign. The Foundation has a fundraising goal of $3.5M and to date, they have raised and received pledges for $3.2M! To learn more about the Sun Prairie Public Library Foundation’s Capital Campaign, please visit their donation page. 

Renderings

Image
The addition to the library, seen from Linnerud Drive
Image
A rendering of the library entrance
Image
A photo of the Kind Stage and Amphitheater

Timeline and Milestone Events

Capital campaign--Public phase (2024/2025)

Groundbreaking Ceremony (June 11, 2024)

Construction begins (2024)

  • Phase 1 (June 2024 – June 2025)
  • Phase 2 (June 2025 – November 2025)
  • Phase 3 (December 2025 – January 2026)
  • Phase 4 (January 2026 – March 2026)

Ribbon cutting for expanded building! (March 2026)

Construction Updates

Image
Library Expansion Update - October 2024

Click the image above to access this month's Library Expansion Update video, brought to you by the Sun Prairie Media Center. 

Additional Information
If you have additional questions, or would like to support the future needs of the Sun Prairie Public Library, contact Svetha Hetzler, Library Director at 825-0900 or by email at shetzler [at] sunlib.org (shetzler[at]sunlib[dot]org).